Fredericton International Airport Authority Terminal Expansion and Renovation

Fredericton, New Brunswick

completeRegional And Local AirportsNRP
Federal contribution
$9.0M
$9,000,000
Federal share31%

of $29.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 1, 2018
201920202021
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jun 1, 2019(actual)
Construction end
Feb 19, 2021(actual)

Against the original forecast

  • Construction end7 weeks lateforecast Jan 1, 2021