CAFN Phase II Subdivision Expansion Project - Local Roads

Haines Junction, Yukon

completeHighways and RoadsMRIF
Federal contribution
$27,613
Federal share33%

of $82.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 18, 2005
200620072008
Built
Program
Municipal Rural Infrastructure Fund
Construction start
May 1, 2008(actual)
Construction end
Jul 31, 2008(actual)

Against the original forecast

  • Construction start2.9 years lateforecast Jun 1, 2005
  • Construction end2.8 years lateforecast Sep 30, 2005

Also in Haines Junction

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12801 in the federal list. How to read these figures.