Phase 3 - Poplar Park
Federal contribution
$250,000
Federal share16%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 27, 2006
2006200720082009
Built
Approved 5 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of White City
- Construction start
- Oct 31, 2005(actual)
- Construction end
- Dec 9, 2008(actual)
Against the original forecast
- Construction start5 months earlyforecast Apr 1, 2006
- Construction end20 months lateforecast Mar 31, 2007
Also in White City