Wastewater Treatment Facility in White City
Federal contribution
$7.3M
$7,303,333
Federal share25%
of $29.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 27, 2017
20172019202120232025
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- WCRM158 Wastewater Management Authority Inc.
- Construction start
- Jan 10, 2018(actual)
- Construction end
- Dec 22, 2025(actual)
Against the original forecast
- Construction end3 weeks lateforecast Nov 30, 2025