White City Wastewater Improvements
Federal contribution
$1.6M
$1,586,666
Federal share33%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
201020112012
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Jan 15, 2010(actual)
- Construction end
- Feb 28, 2012(actual)
Against the original forecast
- Construction start6 weeks lateforecast Dec 1, 2009
- Construction end4 weeks lateforecast Jan 31, 2012