New Water Treatment Plant

Macklin, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$250,000
Federal share16%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2005
200620072008
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Macklin
Construction start
Jul 31, 2005(actual)
Construction end
Jan 25, 2008(actual)

Against the original forecast

  • Construction start2 months earlyforecast Sep 30, 2005
  • Construction end10 months lateforecast Mar 31, 2007

Also in Macklin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12809 in the federal list. How to read these figures.