Town of Macklin - Cast Iron Water Main Replacement
Federal contribution
$722,926
Federal share40%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2021
20212022
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Macklin
- Construction start
- Oct 19, 2021(actual)
- Construction end
- Jul 27, 2022(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2021
- Construction end4 weeks lateforecast Jun 30, 2022
Also in Macklin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57420 in the federal list. How to read these figures.