completeWastewaterCC
Federal contribution
$820,000
Federal share33%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Macklin
Construction start
Jul 25, 2011(actual)
Construction end
Oct 5, 2012(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 1, 2011
  • Construction end4 weeks earlyforecast Oct 31, 2012