Sewage Lagoon Expansion
Federal contribution
$820,000
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2009
201020112012
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Macklin
- Construction start
- Jul 25, 2011(actual)
- Construction end
- Oct 5, 2012(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 1, 2011
- Construction end4 weeks earlyforecast Oct 31, 2012
Also in Macklin