Millennium Library Park Redevelopment

Winnipeg, Manitoba

completeRecreationMRIF
Federal contribution
$700,000
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2005
2006200820102012
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jan 1, 2007(actual)
Construction end
Aug 22, 2012(actual)

Against the original forecast

  • Construction start19 months lateforecast May 18, 2005
  • Construction end6.1 years lateforecast Jul 1, 2006

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12985 in the federal list. How to read these figures.