Water and Sewer Main Replacement
Fort Simpson, Northwest Territories
Federal contribution
$471,560
Federal share35%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20072009201120132015
Built
Approved 9.6 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Fort Simpson
- Construction start
- Aug 23, 2006(actual)
- Construction end
- Mar 21, 2012(actual)
Against the original forecast
- Construction start12 months lateforecast Sep 1, 2005
- Construction end5 years lateforecast Mar 31, 2007
Also in Fort Simpson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13107 in the federal list. How to read these figures.