Sunset Drive Water Main Placement
Kensington, Prince Edward Island
Federal contribution
$55,874
Federal share28%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 13, 2005
20062007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Kensington
- Construction start
- Dec 1, 2005(actual)
- Construction end
- Sep 30, 2007(actual)
Against the original forecast
- Construction start6 weeks lateforecast Oct 20, 2005
- Construction end14 months lateforecast Jul 28, 2006
Also in Kensington
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13171 in the federal list. How to read these figures.