St. Stephen - Calais Highway Access and Border Crossing
Federal contribution
$30.0M
$30,000,000
Federal share50%
of $60.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedNov 18, 2003
ApprovedOct 7, 2004
2004200620082010
Built
Approved 11 months after the announcement.
- Program
- Border Infrastructure Fund
- Ultimate recipient
- Province of New Brunswick
- Construction start
- May 1, 2006(actual)
- Construction end
- Nov 1, 2009(actual)