Back to projects

McAdam - Wellfield Expansion

McAdam, New Brunswick

completeDrinking WaterCVRIS
Federal contribution
$760,000
Federal share80%

of $950.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 5, 2021
2021202220232024
Built

Approved 8 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Village of McAdam
Construction start
May 1, 2022(actual)
Construction end
May 24, 2024(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast Jun 27, 2022
  • Construction end5 months lateforecast Dec 31, 2023

Also in McAdam