McAdam - Wellfield Expansion - Phase 2
Federal contribution
$131,100
Federal share60%
of $218.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
2024
Built
Approved 17 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of McAdam
- Construction start
- Sep 29, 2023(actual)
- Construction end
- May 31, 2024(actual)
Against the original forecast
- Construction start5 months lateforecast May 8, 2023
- Construction end3 months earlyforecast Aug 31, 2024