Borden-Carleton Sewer Main Extension
Borden-Carleton, Prince Edward Island
Federal contribution
$227,284
Federal share33%
of $681.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 13, 2005
200620072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community of Borden-Carleton
- Construction start
- Apr 24, 2006(actual)
- Construction end
- Feb 26, 2008(actual)
Against the original forecast
- Construction start6 months lateforecast Oct 20, 2005
- Construction end20 months lateforecast Jun 16, 2006
Also in Borden-Carleton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13273 in the federal list. How to read these figures.