Northumberland Strait Submarine Transmission System

Borden-Carleton, Prince Edward Island

completeGreen EnergyGIF
Federal contribution
$45.7M
$45,667,567
Federal share50%

of $91.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 20, 2015
ApprovedJul 23, 2015
20162017
Built

Approved 4 months after the announcement.

Program
Green Infrastructure Fund
Construction start
Apr 29, 2016(actual)
Construction end
Jun 30, 2017(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Mar 1, 2016
  • Construction end15 months earlyforecast Sep 30, 2018

Also in Borden-Carleton