Northumberland Strait Submarine Transmission System (top-up)
Borden-Carleton, Prince Edward Island
Federal contribution
$19.0M
$18,985,000
Federal share50%
of $38.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 20, 2015
ApprovedOct 19, 2016
20162017
Built
Approved 19 months after the announcement.
- Program
- Green Infrastructure Fund
- Ultimate recipient
- Province of Prince Edward Island
- Construction start
- Apr 29, 2016(actual)
- Construction end
- Jun 30, 2017(actual)
Against the original forecast
- Construction start8 weeks lateforecast Mar 1, 2016
- Construction end15 months earlyforecast Sep 30, 2018
Also in Borden-Carleton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51769 in the federal list. How to read these figures.