Winnipeg Wastewater Treatment
Federal contribution
$42.0M
$42,000,000
Federal share30%
of $140.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 22, 2005
20052010201520202025
Built
Approved 7 months after the announcement.
- Program
- Canada Strategic Infrastructure Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Apr 14, 2008(actual)
- Construction end
- Feb 27, 2026(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Mar 31, 2026
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13301 in the federal list. How to read these figures.