Construct New Tignish Centennial Arena
Federal contribution
$1.1M
$1,066,291
Federal share33%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
20072008200920102011
Built
Approved 2 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Sports Recreation Association of Tignish
- Construction start
- Apr 5, 2006(actual)
- Construction end
- May 15, 2011(actual)
Against the original forecast
- Construction end4.1 years lateforecast Apr 1, 2007
Also in Tignish
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13312 in the federal list. How to read these figures.