Dalton Avenue Rehabilitation

Tignish, Prince Edward Island

completeHighways and RoadsISF
Federal contribution
$450,000
Federal share50%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 4, 2009
ApprovedJun 15, 2009
Built
Program
Infrastructure Stimulus Fund
Construction start
Jul 14, 2009(actual)
Construction end
Oct 22, 2009(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Nov 15, 2009

Also in Tignish

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29106 in the federal list. How to read these figures.