Tignish Co-operative Association Limited Community Outreach Expansion
Federal contribution
$303,499
Federal share40%
of $758.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 21, 2020
20202021
Built
Approved 6 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Tignish Health Cooperative
- Construction start
- Sep 21, 2020(actual)
- Construction end
- Mar 31, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2020
- Construction end2 months lateforecast Jan 28, 2021
Also in Tignish
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55245 in the federal list. How to read these figures.