Wellington Sewer Main Extension
Wellington, Prince Edward Island
Federal contribution
$106,164
Federal share32%
of $327.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 13, 2005
2006200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community of Wellington
- Construction start
- Aug 1, 2006(actual)
- Construction end
- Aug 31, 2009(actual)
Against the original forecast
- Construction start9 months lateforecast Oct 20, 2005
- Construction end3 years lateforecast Aug 30, 2006
Also in Wellington
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13317 in the federal list. How to read these figures.