Wellington Lagoon Expansion
Wellington, Prince Edward Island
Federal contribution
$332,000
Federal share33%
of $996.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Community of Wellington
- Construction start
- Jun 29, 2010(actual)
- Construction end
- Jul 30, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 30, 2010
- Construction end9 months lateforecast Oct 30, 2010
Also in Wellington
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26517 in the federal list. How to read these figures.