Back to projects

Active residents for a better health

Wellington, Prince Edward Island

completeActive TransportationATF
Federal contribution
$239,958
Federal share59%

of $404.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2024
20232024
Built

Approved 18 months before the announcement.

Program
Active Transportation Fund
Construction start
Sep 1, 2023(actual)
Construction end
Oct 15, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 30, 2023
  • Construction end2 weeks lateforecast Sep 29, 2023

Also in Wellington