Pilot Mound Millennium Recreation Complex
Federal contribution
$285,000
Federal share15%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 23, 2007
20082009
Built
Approved 5 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Pilot Mound Millennium Recreation Complex Inc.
- Construction start
- Feb 13, 2007(actual)
- Construction end
- May 26, 2009(actual)
Against the original forecast
- Construction start18 months lateforecast Jul 31, 2005
- Construction end5 months lateforecast Dec 31, 2008
Also in Louise
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13318 in the federal list. How to read these figures.