Wastewater Lagoon Expansion and Upgrade

Louise, Manitoba

completeWastewaterISF
Federal contribution
$342,121
Federal share33%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Crystal City
Construction start
Jun 28, 2010(actual)
Construction end
Sep 30, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 1, 2010
  • Construction end4 weeks earlyforecast Oct 31, 2011