Wastewater Lagoon Expansion and Upgrade
Federal contribution
$342,121
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Crystal City
- Construction start
- Jun 28, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 1, 2010
- Construction end4 weeks earlyforecast Oct 31, 2011
Also in Louise
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29464 in the federal list. How to read these figures.