Thomas Greenway Middle Years School - Steam Boiler System Replacement and Ventilation System Upgrade
Federal contribution
$343,440
Federal share80%
of $429.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 19, 2023
2024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of Manitoba
- Construction start
- Sep 1, 2023(actual)
- Construction end
- Jun 26, 2024(actual)
Against the original forecast
- Construction start7 months lateforecast Feb 15, 2023
- Construction end5 months lateforecast Feb 1, 2024