Main Street Sewer Repairs

O'Leary, Prince Edward Island

completeWastewaterMRIF
Federal contribution
$55,017
Federal share31%

of $175.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 13, 2005
20062007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Community of O'Leary
Construction start
Jul 1, 2006(actual)
Construction end
Mar 1, 2007(actual)

Against the original forecast

  • Construction start8 months lateforecast Oct 20, 2005
  • Construction end6 months lateforecast Aug 31, 2006

Also in O'Leary

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13320 in the federal list. How to read these figures.