Main Street Sewer Repairs
Federal contribution
$55,017
Federal share31%
of $175.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 13, 2005
20062007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community of O'Leary
- Construction start
- Jul 1, 2006(actual)
- Construction end
- Mar 1, 2007(actual)
Against the original forecast
- Construction start8 months lateforecast Oct 20, 2005
- Construction end6 months lateforecast Aug 31, 2006
Also in O'Leary
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13320 in the federal list. How to read these figures.