Upgrade and New Construction of Water Treatment Plant in West Elgin
Federal contribution
$9.8M
$9,797,985
Federal share45%
of $21.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
20072008200920102011
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of West Elgin
- Construction start
- May 1, 2006(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction start17 months lateforecast Nov 15, 2004
- Construction end5 months earlyforecast Mar 31, 2011
Also in West Elgin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13372 in the federal list. How to read these figures.