Reconstruction of a Section of Blacks Road
Federal contribution
$719,400
Federal share60%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2019
202020212022202320242025
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of West Elgin
- Construction start
- Oct 3, 2022(actual)
- Construction end
- Oct 23, 2024(actual)
Against the original forecast
- Construction end8 months earlyforecast Jun 30, 2025
Also in West Elgin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54616 in the federal list. How to read these figures.