West Lorne Sewage System Upgrades
Federal contribution
$950,516
Federal share33%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 7, 2016
2017201820192020
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of West Elgin
- Construction start
- Nov 5, 2018(actual)
- Construction end
- May 31, 2020(actual)
Against the original forecast
- Construction end5 months lateforecast Dec 31, 2019
Also in West Elgin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46881 in the federal list. How to read these figures.