Uprading of the Bancroft Waste Water Treatment Plant
Federal contribution
$3.2M
$3,219,167
Federal share33%
of $9.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009201020112012
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Bancroft
- Construction start
- Jul 19, 2006(actual)
- Construction end
- Nov 4, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 24, 2006
- Construction end17 months earlyforecast Mar 31, 2013
Also in Bancroft
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13796 in the federal list. How to read these figures.