Construction of the Faraday Landfill Leachate Management System
Federal contribution
$778,264
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Faraday
- Construction start
- Jul 1, 2009(actual)
- Construction end
- Dec 31, 2012(actual)
Also in Bancroft
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23213 in the federal list. How to read these figures.