Air Conditioning Centennial Manor Long-Term Care
Federal contribution
$625,673
Federal share80%
of $782.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
20222023
Built
Approved 3 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- The Corporation of the County of Hastings - Hastings Centennial Manor
- Construction start
- Mar 28, 2021(actual)
- Construction end
- Oct 31, 2023(actual)
Against the original forecast
- Construction start5 weeks earlyforecast May 3, 2021
- Construction end2.1 years lateforecast Sep 6, 2021
Also in Bancroft
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59470 in the federal list. How to read these figures.