Replacement of New Sarum Bridge

Central Elgin, Ontario

completeHighways and RoadsMRIF
Federal contribution
$494,502
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
200720082009
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
County of Elgin
Construction start
Apr 20, 2006(actual)
Construction end
Feb 10, 2009(actual)

Against the original forecast

  • Construction start13 months lateforecast Apr 1, 2005
  • Construction end19 months lateforecast Jun 30, 2007

Also in Central Elgin