Replacement of New Sarum Bridge
Federal contribution
$494,502
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Elgin
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Feb 10, 2009(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2005
- Construction end19 months lateforecast Jun 30, 2007
Also in Central Elgin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 13840 in the federal list. How to read these figures.