Construction of New Sanitary Sewage Pumping Station to Replace Station #51

Central Elgin, Ontario

completeWastewaterCWWF
Federal contribution
$431,647
Federal share46%

of $941.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20172018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Dec 1, 2016(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jan 2, 2017
  • Construction end5 months lateforecast Apr 30, 2018

Also in Central Elgin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49028 in the federal list. How to read these figures.