Eastwood Park Upgrades
Federal contribution
$286,000
Federal share40%
of $715.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Central Elgin
- Construction start
- Jul 12, 2021(actual)
- Construction end
- Jun 22, 2022(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Sep 1, 2021
- Construction end2 months earlyforecast Sep 1, 2022
Also in Central Elgin