Back to projects

Nunavut Housing Infrastructure

Iqaluit, Nunavut

completeAffordable And Temporary HousingCSIF
Federal contribution
$20.0M
$20,000,000
Federal share50%

of $40.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 8, 2003
ApprovedMar 2, 2005
2004200520062007
Built

Approved 17 months after the announcement.

Program
Canada Strategic Infrastructure Fund
Ultimate recipient
Nunavut Housing Corporation
Construction start
Apr 1, 2004(actual)
Construction end
Mar 31, 2007(actual)

Also in Iqaluit