Replacement of Gibson Street Watermains, Storm and Sanitary Sewers

Parry Sound, Ontario

completeDrinking WaterMRIF
Federal contribution
$1.2M
$1,150,008
Federal share33%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
200720082009
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Parry Sound
Construction start
Apr 20, 2006(actual)
Construction end
Aug 31, 2009(actual)

Against the original forecast

  • Construction start7 months lateforecast Sep 6, 2005
  • Construction end8 months lateforecast Dec 31, 2008

Also in Parry Sound