West Parry Sound Area Recreation and Culture Centre joint project between 7 Municipalities and 2 First Nations Communities
Federal contribution
$12.8M
$12,760,307
Federal share40%
of $31.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
20222023202420252026
BuiltForecast
Approved 6 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- West Parry Sound Recreation and Cultural Centre
- Construction start
- Mar 24, 2024(actual)
- Construction end
- May 31, 2026(forecast)
Also in Parry Sound
- Highway 69 Project; Four-Lane Expansion from Highway 529 to Highway 522$120.0M
- Highway 69 Project; 4-Lane Expansion, Highway 559 Northerly$49.3M
- Upgrading of Parry Sound Wastewater Treatment Plant$5.3M
- Highway 518 - East of Highway 400 towards Orrville$2.0M
- Replacement of Gibson Street Watermains, Storm and Sanitary Sewers$1.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58203 in the federal list. How to read these figures.