Highway 518 - East of Highway 400 towards Orrville
Federal contribution
$2.0M
$2,050,000
Federal share50%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 7, 2010
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Apr 21, 2010(actual)
- Construction end
- Dec 7, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2010
- Construction end3 weeks earlyforecast Dec 30, 2010
Also in Parry Sound
- Highway 69 Project; Four-Lane Expansion from Highway 529 to Highway 522$120.0M
- Highway 69 Project; 4-Lane Expansion, Highway 559 Northerly$49.3M
- West Parry Sound Area Recreation and Culture Centre joint project between 7 Municipalities and 2 First Nations Communities$12.8M
- Upgrading of Parry Sound Wastewater Treatment Plant$5.3M
- Replacement of Gibson Street Watermains, Storm and Sanitary Sewers$1.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39803 in the federal list. How to read these figures.