Replacement of Deacon Bridge

Perth, Ontario

completeHighways and RoadsMRIF
Federal contribution
$177,570
Federal share33%

of $532.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
200720082009
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
County of Lanark
Construction start
Jul 1, 2006(actual)
Construction end
Sep 2, 2009(actual)

Against the original forecast

  • Construction end17 months lateforecast Mar 31, 2008