Reconstruction and Widening of 21.4 km of Road 38
Federal contribution
$2.0M
$2,011,602
Federal share33%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
20072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Central Frontenac
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Feb 22, 2008(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2006
- Construction end8 weeks lateforecast Dec 31, 2007
Also in Central Frontenac
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14039 in the federal list. How to read these figures.