Back to projects

Reconstruction and Widening of 21.4 km of Road 38

Central Frontenac, Ontario

completeHighways and RoadsMRIF
Federal contribution
$2.0M
$2,011,602
Federal share33%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Apr 20, 2006(actual)
Construction end
Feb 22, 2008(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Apr 1, 2006
  • Construction end8 weeks lateforecast Dec 31, 2007

Also in Central Frontenac

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14039 in the federal list. How to read these figures.