Retrofits and Renovations to Administration Office

Central Frontenac, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
20222023
Built

Approved 6 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 10, 2022(actual)
Construction end
Dec 20, 2022(actual)

Against the original forecast

  • Construction start7 months earlyforecast Sep 1, 2022
  • Construction end3 months earlyforecast Mar 31, 2023

Also in Central Frontenac

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59630 in the federal list. How to read these figures.