Road Upgrade and Construction

Central Frontenac, Ontario

completeHighways and RoadsISF
Federal contribution
$789,132
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 11, 2009(actual)
Construction end
Oct 29, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2009
  • Construction end2 months earlyforecast Dec 31, 2010