Replacement of the Durham Creek Bridge

Enniskillen, Ontario

completeHighways and RoadsMRIF
Federal contribution
$114,173
Federal share33%

of $342.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Enniskillen
Construction start
Apr 20, 2006(actual)
Construction end
Apr 21, 2008(actual)

Against the original forecast

  • Construction start9 months lateforecast Aug 1, 2005
  • Construction end4 months lateforecast Dec 31, 2007

Also in Enniskillen

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14047 in the federal list. How to read these figures.