Back to projects

Marthaville Road Rehabilitation

Enniskillen, Ontario

completeHighways and RoadsISF
Federal contribution
$173,049
Federal share33%

of $519.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Enniskillen
Construction start
May 1, 2010(actual)
Construction end
Jun 21, 2010(actual)

Against the original forecast

  • Construction end3 months earlyforecast Sep 15, 2010

Also in Enniskillen

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31319 in the federal list. How to read these figures.