Replacement of Black Creek Bridge

Enniskillen, Ontario

completeHighways and RoadsMRIF
Federal contribution
$189,603
Federal share33%

of $568.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
200720082009
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Enniskillen
Construction start
Mar 1, 2007(actual)
Construction end
Oct 16, 2009(actual)

Against the original forecast

  • Construction end2 months earlyforecast Dec 31, 2009

Also in Enniskillen

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15345 in the federal list. How to read these figures.