Replacement of Black Creek Bridge
Federal contribution
$189,603
Federal share33%
of $568.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
200720082009
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Enniskillen
- Construction start
- Mar 1, 2007(actual)
- Construction end
- Oct 16, 2009(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 31, 2009
Also in Enniskillen
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15345 in the federal list. How to read these figures.