Expansion of the Recycling Depot and Closure of the McKellar Landfill Site
Federal contribution
$124,610
Federal share33%
of $373.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2006
2007200820092010
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of McKellar
- Construction start
- Apr 20, 2006(actual)
- Construction end
- Mar 15, 2010(actual)
Against the original forecast
- Construction end8 months earlyforecast Oct 31, 2010