Back to projects

Middle River Bridge Replacement

McKellar, Ontario

completeHighways and RoadsISF
Federal contribution
$710,056
Federal share31%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of McKellar
Construction start
Jan 4, 2010(actual)
Construction end
Oct 31, 2011(actual)

Also in McKellar

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31922 in the federal list. How to read these figures.